Progress Report on the Utilisation of Maintenance Grant of Block Panchayats in districts for the month of March 2008 (Provisional) (Alappuzha Dist.)
Sl No
Name of block Panchayats
Allocation for the year  2007-08
Total Amount Released upto the end of the Month
Opening Balance as on 1-4-07
Total Fund  (Col 4+5)
Total Expenditure up to the end of the Month
No. of maintanance works approved for the Year
No. Maintanance works started
No. of Mintanance works completed
No. of  works in progress
% of Expenditure against Allocation
% of Expenditure against total fund
1
2
3
4
5
6
7
8
9
10
11
12
13
1 Ambalapuzha
1234000
1234000
69004
1303004
100000
4
0
1
1
8
8
2 Aryad
1088000
1088000
402710
1490710
270874
5
0
3
2
25
18
3 Bharanikavu
1510000
1510000
133757
1643757
229372
7
0
2
6
15
14
4 Champakulam
1437000
1437000
0
1437000
380000
6
0
2
6
26
26
5 Chengannur
1565000
1565000
0
1565000
457060
7
0
1
6
29
29
6 Harippad
1639000
1639000
173028
1812028
0
0
0
0
0
0
0
7 Kanjikuzhi
1455000
1455000
354035
1809035
148457
8
0
3
5
10
8
8 Mavelikara
1185000
1185000
337621
1522621
0
5
0
0
5
0
0
9 Muthukulam
1478000
1478000
791532
2269532
488539
9
0
2
7
33
22
10 Pattanakkad
1834000
1834000
74664
1908664
100000
4
0
0
3
5
5
11 Thaicattussery
988000
988000
347463
1335463
29697
7
0
0
7
3
2
12 Veliyanad
1108000
1108000
383242
1491242
158036
8
0
3
4
14
11
Dist. Total
16521000
16521000
3067056
19588056
2362035
70
0
17
52
14
12

Source: Rural Development Commissionerate, Govt. of Kerala
* Budget provision for the financial year 2007-2008
** Opening balance as on 01/04/2007